Analisis Waktu dan Biaya Perbandingan Erection Steel Box Girder Menggunakan Metode Skid Launching dan Launcher
Abstract
This research was conducted on the construction project of Cimanggis - Cibitung toll road section 2 Sta. 27+070 to Sta. 50+353. The background of this research is the need to know a more efficient implementation method in terms of time and cost, given the importance of effectiveness and efficiency in construction projects. The purpose of this research is to determine the time of girder erection work using the skid launching method and the girder launcher method, Knowing the cost of implementing girder erection work with both methods, Comparing the efficiency of time and cost between the skid launching method and the girder launcher method, The data that has been obtained is analysed. From the results of the analysis of the two tools obtained the results of the erection process, namely the Launcher girder method is more efficient in the time of erection of steel box girder, requiring 6356 minutes compared to 7500 minutes in the Skid Launching method, the data obtained in terms of time while in terms of cost the Launcher girder method is more economical with a cost of Rp 13,867,349 per span compared to Rp 35,767,019 in the Skid Launching method. resulting in cost savings of IDR 21,899,669 or around 39%.From the data obtained, we can determine the most efficient method in terms of time and cost between the two methods. The methodology used in this study includes primary and secondary data collection, analysis of material requirements, productivity and duration of work, and cost analysis. The results showed that the girder launcher method is more efficient in terms of time and cheaper in terms of cost compared to the skid launching method. The findings are expected to serve as a reference in the implementation of similar projects in the future.
References
Peranan Strategis Jaringan Tol Jorr 2 Bagi Kawasan Jabodetabek, https://www.antaranews.com/berita/3937164
Industrie, P. B. (2022). Work Method Statement Erection Steel Box Girder Span P37-P38 elevated Transyogi Proyek Pembangunan Jalan Tol cimanggis - cibitung seksi 2 sta 27+070 - sta 50+373. bogor: PT Bakrie Metal Industrie.
Karya, P. w. (2022). Work Method Statetment Erection Steel Box Girder Span P37-P38-P39 Elevated Transyogi Proyek Pembangunan jalan Tol Cimnggis - Cibitung Seksi 2 Sta 27+070 - Sta 50+373. Bogor: PT. Waskita Karya.
Putra, I. K. (2020). Pengaruh Percepatan Waktu Pelaksaan Proyek . Pengaruh Percepatan Waktu Pelaksaan Proyek Konstruksi Gedung Terhadap Biaya Pelaksanaan, 43-45.
Setiawan, A. (2008). Perencanaan Struktur Baja dengan Metode LRFD. Jakarta: Erlanga.
S. F. Rostiyanti, Alat Berat Untuk Proyek Konstruksi, Jakarta: Rineka Cipta, 2008
Sugiyono, Metode Penelitian Kuantitatif Kualitatif dan R&D, Bandung: Alfabeta, 2011..
T. J. W. Dwi Dian Pratama, "Analisa Perbandingan Metode Erection Girder Menggunakan Launcher Girder dan Temporary
Peranan Strategis Jaringan Tol Jorr 2 Bagi Kawasan Jabodetabek,
https://www.antaranews.com/berita/3937164
Industrie, P. B. (2022). Work Method Statement Erection Steel Box Girder Span P37-P38 elevated Transyogi Proyek Pembangunan Jalan Tol cimanggis - cibitung seksi 2 sta 27+070 - sta 50+373. bogor: PT Bakrie Metal Industrie.
Karya, P. w. (2022). Work Method Statetment Erection Steel Box Girder Span P37-P38-P39 Elevated Transyogi Proyek Pembangunan jalan Tol Cimnggis - Cibitung Seksi 2 Sta 27+070 - Sta 50+373. Bogor: PT. Waskita Karya.
Putra, I. K. (2020). Pengaruh Percepatan Waktu Pelaksaan Proyek . Pengaruh Percepatan Waktu Pelaksaan Proyek Konstruksi Gedung Terhadap Biaya Pelaksanaan, 43-45.
Setiawan, A. (2008). Perencanaan Struktur Baja dengan Metode LRFD. Jakarta: Erlanga.
S. F. Rostiyanti, Alat Berat Untuk Proyek Konstruksi, Jakarta: Rineka Cipta, 2008
Sugiyono, Metode Penelitian Kuantitatif Kualitatif dan R&D, Bandung: Alfabeta, 2011..
T. J. W. Dwi Dian Pratama, "Analisa Perbandingan Metode Erection Girder Menggunakan Launcher Girder dan Temporary Bridge dari Segi Biaya dan Waktu pada Jembatan Kali Surabaya Mojokerto," Jurnal Teknik Pomits, 2013
Kristijanto, Heppy; Supani. (2007). “ Analisa Pemilihan Keputusan Metode Pelaksanaan Erection Girder Tipe - I Dengan Metode Ahp ( Studi Kasus : Causeway Jembatan Suramadu Sisi Madura)”. Jurnal Pondasi. 13 (2), 156.
Bunga Islami Fortuna. (2021). Analisis Waktu dan Biaya Perbandingan Erection Box Girder. Jurnal Ilmiah Rekayasa Sipil , 107-110.
Copyright (c) 2024 Jurnal Ilmiah Rekayasa Sipil
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.