Evaluasi Pelaksanaan Overhaul Pabrik Indarung VI Pada Masa Pandemu di Tahun 2020

  • Ridwan Muchtar Universitas Andalas
  • Benny Dwika Leonanda Program Profesi Insinyur, Fakultas Teknik, Universitas Andalas
Keywords: Overhaul, Project Management, Pandemic

Abstract

Overhaul activity is one periodic maintenance by the company to recondition production equipment in order to
operate with high avaibility and realibility. Overhaul activities can also be referred to as project based on a series of work that occirs unique, complex, done in a certain period of time and resources. This factory overhaul project must be completed on time, according to quality and cost as well as zero accident. In connection with the condition of the Covid-19 pandemic, the work is carried out with the Covid-19 health protocol so that ts does
not become a source of new spread. In this paper will be discussed the implementation of the overhaul of the
plant Indarung VI Year 2020 in the pandemic, starting from the stages of planning, preparation, implementation and evaluation (feedback). The realization of work time experienced delays of 2,68 days, quality according to standards and with the realization of a greater cost of Rp. 2.22 Billion. During the overhaul project there were 3 cases of work accidents and there were no additional cases of Covid-19 in the workforce involved in the project.

References

AS. Corder. 1988. Teknik Manajemen Pemeliharaan. edisi 2. Erlangga, Jakarta.

Ebeling, Charles E. 1997. An Introduction to Reliability and aintainability Engineering, Me Graw Hill Book Co.,

Singapore

Agus Sugiarto., Teguh Wahyono. 2015. Manajemen Kearsipan Modern. Yogyakarta: GAVA MEDIA

Handoko, T. Hani. 2012. Manajemen Personalia dan Sumber Daya Manusia. Yogyakarta. BPFE Husen, Abrar, 2009, Manajemen Proyek (Perencanaan Penjadwalan dan Pengendalian Proyek), Penerbit: Andi Yogyakarta

Ahyari, A. 2002, Manajemen Produksi Perencanaan Sistem Produksi Buku 1,Edisi Keempat, Yogyakarta: BPFE UGM.

Haming, M., dan Mahmud Nurnajamuddin., 2011. Manajemen Produksi Modern Operasi Manufaktur dan Jasa. Jakarta: Bumi Aksara.

Assauri, Sofjan. 2004. Manajemen Pemasaran. Jakarta: Rajawali Pres

Manahan P. Tampubolon. 2014. Manajemen Operasi & Rantai Pemasok (Operation and Supply-chain Management). edisi pertama. Jakarta: Mitra Wacana Media Sarno,

Riyanarto, 2012. Analisis dan Desain Berorientasi Servis Aplikasi Manajemen Proyek, Penerbit Andi,

Bakhtiyar A. dkk. 2012. Analisis faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi pembangunan gedung di kota lamongan.

Ismael, Idzurnida. 2013. Keterlambatan Proyek Konstruksi Gedung Faktor Penyebab dan Tindakan Pencegahannya. Jurnal Momentum Vol.14 No.1

Published
2022-07-08
How to Cite
Muchtar, R., & Leonanda, B. D. (2022). Evaluasi Pelaksanaan Overhaul Pabrik Indarung VI Pada Masa Pandemu di Tahun 2020. Jurnal Teknik Mesin, 15(1), 46-54. https://doi.org/10.30630/jtm.15.1.799